The ExoMars Rosalind Franklin mission would launch in the July–August 2020 window and reach Mars in March 2021.
Source-backed summary; not presented as a verbatim quotation.
European Space Agency ExoMars project
European intergovernmental space agency · European Space Agency
The world at the time.
ESA maintained its 2020 schedule while hardware was completing final tests. The next available Mars transfer opportunity after a missed window was two years later.
What happened.
ESA and Roscosmos announced in March 2020 that launch would be postponed to 2022. Additional component testing and pandemic restrictions prevented the planned 2020 launch.
Predicted vs actual.
| Metric | Predicted | Actual | Variance / caveat |
|---|---|---|---|
| Launch window | July–August 2020 | Not launched in 2020; postponed in March | Original window missed |
The counter-signal.
High-altitude parachute tests in May and August 2019 damaged main canopies despite design changes. Those failures preceded the October schedule update and made qualification a visible source of deadline risk.
Verdict.
Reasoning: contested · Outcome: wrong
The 2020 launch-date forecast was wrong, irrespective of whether the mission eventually launches. The later 2022 cancellation after Russia’s invasion is a separate forecast failure and is not used to explain the 2020 miss.
Cause of death / explanatory lens.
The lesson.
Does the schedule allow enough time to redesign and repeat a failed critical test?
Sources.
- ExoMars parachute progressprimary · 2019-10-15 · claim
- ExoMars to take off for the Red Planet in 2022primary · 2020-03-12 · outcome
- ExoMars parachute testing continuesprimary · 2019-08-12 · counter_signal
Related predictions.
Demographics
United States
Science
United States
Environment
United States