early · Unscored / disputed
ENEC's September 2014 indicative timetable put Barakah Unit 1's commercial operation in 2017.
Source-backed summary; not presented as a verbatim quotation.
Emirates Nuclear Energy Corporation
Developer of the Barakah nuclear power plant · United Arab Emirates
The world at the time.
ENEC reported Unit 1 more than 57% complete and presented the project as on time. Its published calendar was explicitly an indicative project timetable rather than an independent probabilistic forecast.
What happened.
Unit 1 began commercial operation on 6 April 2021. Start-up and grid connection occurred in 2020, which are distinct milestones and do not satisfy the 2017 commercial-operation target.
Predicted vs actual.
| Metric | Predicted | Actual | Variance / caveat |
|---|---|---|---|
| Unit 1 commercial operation | 2017 | 2021-04-06 | About four calendar years later |
The counter-signal.
The 2014 announcement described an 18-month regulatory review for the later units. This showed regulatory work was a separate dependency, although it did not itself predict the Unit 1 delay.
Verdict.
Reasoning: contested · Outcome: partial
This is an early project target: the planned technology became operational after its stated year. Evidence supports the timing miss but is insufficient to assign poor reasoning solely because the timetable slipped.
Cause of death / explanatory lens.
The lesson.
Which commissioning dependencies deserve their own uncertainty range in a construction timetable?
Sources.
- Unit 1 more than 57% completeprimary · 2014-09-17 · claim and contemporary dependency
- Unit 1 started commercial operationsprimary · 2021-04-06 · outcome
- Regulatory licencesprimary · Date not established · licence chronology